DANGLER NOT TO BE USED :

To ensure the correct precedence relationship in the arrow diagram, the following questions must be answered as every activity is added to the network.

(a)     What activities must be completed immediately before this activity can start?

(b)     What activities must follow this activity?

(c)     What activities must occur concurrent with this activity?