Uses of slacks and floats in PERT and CPM


1

Uses of slacks and floats in PERT and CPM. (Apr 2006)

 

Slacks:            Slacks are for events. Slacks of all critical events are zero. Slack is the difference in Earliest occurrence time and Latest occurrence time for the event. It represents the margin by which the event occurrence can be delayed.

 

Floats: Floats are for activities. Total, Free, Independent and Interfering floats are types of floats. Floats represent the margin by which activity start times can be delayed without affecting project completion time.

Floats for critical activities are zero. They can not be delayed by any margin.

 


Like it? Share with your friends!

1
Score Tutorial
S’COrE Education is a professional coaching institute to coach for new generation courses. S’COrE has highly experienced faculty with enormous experience and achievement in teaching and industry. We teach each subject in such a manner that even complicated subject feels simple. This helps student to S’COrE-the-Max. Since 1998 S’COrE had university toppers accross courses and subjects. Once you are our student you will also believe S’COrE - the - Best !!

5 Comments


Warning: Undefined array key "html5" in /home/bmsnewco/public_html/wp-content/plugins/facebook-comments-plugin/class-frontend.php on line 140

Facebook comments:

This Website Is For Sale. Email us an offer we cannot refuse on [email protected] :)

X