(C.P.M.)
1.        For the following project :
(i)Â Â Â Â Â Draw network diagram.
(ii)Â Â Â Â Find critical path and project completion time.
(iii)   Identify critical and non – critical activities.
Activity |
Preceding Activity |
Time (days) |
A |
– |
6 |
B |
A |
5 |
C |
A |
2 |
D |
B |
4 |
E |
C |
2 |
F |
D |
1 |
G |
D & E |
5 |
H |
F & G |
3 |
2.        For the following project :
(i)Â Â Â Â Â Draw network diagram.
(ii)Â Â Â Â Find critical path and project completion time.
(iii)   Identify critical and non – critical activities.
Activity |
Preceding Activity |
Time (days) |
A |
– |
4 |
B |
A |
3 |
C |
A |
5 |
D |
B |
1 |
E |
B & C |
2 |
F |
D & E |
2 |
G |
E |
3 |
3.        A small project consists of following activities. Construct a network diagram for the project and identify critical path and project completion time.
Activity |
A |
B |
C |
D |
E |
F |
G |
Preceding Activity |
– |
A |
A |
B |
B, C |
D |
E |
Time (days) |
3 |
2 |
3 |
4 |
2 |
8 |
6 |
4.        A small project consists of following activities. Construct a network diagram for the project and identify critical path and project completion time.
Activity |
A |
B |
C |
D |
E |
F |
G |
Preceding Activity |
– |
– |
A, B |
C |
C |
D |
E |
Time (days) |
5 |
8 |
4 |
3 |
2 |
4 |
2 |