What is Backward Pass?


0

BACKWARD PASS : The project completion time is called as the ‘CONTRACUTAL OBLIGATION TIME’.  is the latest time (TL) by which the last event in the project should occur.

            If the contractual obligation Time is not specified, the earliest time (TE) for the last event should be the value assume by the latest time (TL) of the last event.

Once the TL value for the last event is known, we proceed in the backward direction through the network calculating the values of TL for the earlier events till the start event is reached. If there are more than one activities immerging from an event. The TL values for that event is taken as the minimum of the TL values among different activities. This is called ‘BACKWARD PASS’.

 


Like it? Share with your friends!

0
MT UVA BMS

MT UVA- University, Vocational and Affiliated Education for BMS

2 Comments

Facebook comments:

Choose A Format
Personality quiz
Series of questions that intends to reveal something about the personality
Trivia quiz
Series of questions with right and wrong answers that intends to check knowledge
Poll
Voting to make decisions or determine opinions
Story
Formatted Text with Embeds and Visuals
List
The Classic Internet Listicles
Countdown
The Classic Internet Countdowns
Open List
Submit your own item and vote up for the best submission
Ranked List
Upvote or downvote to decide the best list item
Meme
Upload your own images to make custom memes
Video
Youtube and Vimeo Embeds
Audio
Soundcloud or Mixcloud Embeds
Image
Photo or GIF
Gif
GIF format