What are the 3 different time estimates in PERT?


0

In PERT 3 different time estimates are defined for each activities.

(i)      OPTIMISTIC TIME ESTIMATE :

          This is the shortest time within which an activity can be completed.

Conditions better than normal are expected during the execution of activity and no provisions are made for delay. This time estimate is usually denoted by ‘to

(ii)     PESSIMISTIC TIME ESTIMATE :

          This is the maximum time required for an accomplish on of an activity i.e. It is the time required if the activity is performed under totally abnormal or adverse condition.

It is denoted by ‘tp 

(iii)    MOST LIKELY TIME ESTIMATE :

          This is the estimate of the type which an activity will require under normal circumstances. It is usually denoted by ‘tm’.

The frequency curve of the activity time estimate resemble the b distribution curve with to and tp as an extreme point and tm as the nodal value. Hence the mean time require for the completion of an activity is given by.

Mean Time = to +4 tm +tp/6

 


Like it? Share with your friends!

0
MT UVA BMS

MT UVA- University, Vocational and Affiliated Education for BMS

50 Comments

Facebook comments:

Choose A Format
Personality quiz
Series of questions that intends to reveal something about the personality
Trivia quiz
Series of questions with right and wrong answers that intends to check knowledge
Poll
Voting to make decisions or determine opinions
Story
Formatted Text with Embeds and Visuals
List
The Classic Internet Listicles
Countdown
The Classic Internet Countdowns
Open List
Submit your own item and vote up for the best submission
Ranked List
Upvote or downvote to decide the best list item
Meme
Upload your own images to make custom memes
Video
Youtube and Vimeo Embeds
Audio
Soundcloud or Mixcloud Embeds
Image
Photo or GIF
Gif
GIF format