Direct Material Variance


0

The main reason for actual and estimated costs being different are either a change in the price of materials or a change in the usage of material.

 

Materials price variance is the difference in cost that results from the price being different to the standard. ( Standard price – Actual price ) x Actual material usage

 

Materials usage variance is the difference between the actual usage of material and the standard usage multiplied by the standard price. ( Actual usage – Standard usage ) x Standard price

 

Total material variance = Actual Material cost – Standard Material cost

 

 

 