Guidelines for constructing Network Diagrams:

Advertisement

 

  1. Each activity is represented by only one arrow.
  2. An arrow can represent only one activity
  3. If two or more activities are identified with the same start & end events.  Dummy activity / activities  need to be introduced in the network
  4. Before an activity can be started all preceding activities must be completed
  5. The flow of diagram is from left to right.
  6. The arrows are not to the scale
  7. Arrows should be straight
  8. Unless absolutely unavoidable, arrows should not be crossed.
Advertisement
The following two tabs change content below.
We, at BMS.co.in, believe in sharing knowledge and giving quality information to our BMS students. We are here to provide and update you with every details required by you BMSites! If you want to join us, please mail to [email protected]
2 Comments

Leave a reply

BMS.co.in is aimed at revolutionising Bachelors in Management Studies education, also known as BMS for students appearing for BMS exams across all states of India. We provide free study material, 100s of tutorials with worked examples, past papers, tips, tricks for BMS exams, we are creating a digital learning library.

Disclaimer: We are not affiliated with any university or government body in anyway.

©2020 BMS - Bachelor of Management Studies Community 

A Management Paradise Venture

Ask Us On WhatsApp
or

Log in with your credentials

or    

Forgot your details?

or

Create Account