What is Work-in-progress A/c?


0

Work-in-progress A/c

 

The Work-in-progress A/c is debited with the sums

 

(i)                 Work certified (valued at contract price), and

(ii)               Work done but not yet certified (valued at cost).

 

This account is credited with the balance of the notional profit not taken to the Profit and Loss Account.

 

This account shows debit balance which is taken to the Balance Sheet on the Asset side. The Contractee’s A/c which shows credit balance on account of cash received in advance, is not shown on the Liability side of the Balance Sheet but is shown as a deduction from the Work-in-Progress A/c on the Asset side of the Balance Sheet.


Like it? Share with your friends!

0
BMS Team

We, at BMS.co.in, believe in sharing knowledge and giving quality information to our BMS students. We are here to provide and update you with every details required by you BMSites! If you want to join us, please mail to [email protected].

8 Comments


Warning: Undefined array key "html5" in /home/bmsnewco/public_html/wp-content/plugins/facebook-comments-plugin/class-frontend.php on line 140

Facebook comments: