What is optimality in assignment problem?
Optimal solution to an assignment problem is unique assignment is mad at every row and every column. An optimal solution provides a schedule to obtain...
Optimal solution to an assignment problem is unique assignment is mad at every row and every column. An optimal solution provides a schedule to obtain...
(Based on Step 1, 2, 3) 1. The departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency...
1. For the pay – off matrix given below, find best course of action using : (i) EMV criterion (ii) EOL criterion (iii) Maximin...
Necessary and sufficient conditions for critical path in PERT / CPM. (Apr 2006) Necessary conditions: If Earliest occurrence time equals Latest occurrence time for...
(Project Crashing) 1. For the data given in the table below, draw the network. Crash systematically the activities and determine the optimal project duration...
Activity : An activity in a project is usually viewed as a job requiring time and resources for its completion. An arrow is commonly used...
Peculiar Outsourcing Company Ltd. Has production centers at Mumbai, Chennai, and Kolkata. The company has its distribution centers at Ahmedabad, Bhopal, Bangalore and Goa. Production...
The Assignment problem can be of Minimization type or Maximization type. A Minimization Assignment problem involves cost, time or distance data. The objective of solution...
Network : This is the combination of activities, dummy activities and events in logical sequence according to the rule for drawing networks. A project...