Operations Research Sample Question Paper 2013


0
  1. All questions are compulsory in section I and
  2. Attempt any 3 from section II
  3. Normal distribution table is attached.

Section I

Q.1) answer the following questions briefly                                                                                    (15)

a)      What are the components of formulation of linear programming problems?

b)      What is an assignment problem? How will you deal with assignment problem where some assignments are prohibited?

c)       Name any 3 methods of finding initial basic feasible solution for the transportation problems. Which one of them is best and why?

d)      Distinguish between PERT and CPM network. Give one application of CPM network

e)      What are the objectives of project crashing?

Q.2) from the following data, determine:-

I.            Normal project duration and cost

II.            Optimal project completion time and cost

Activity                                       1-2           1-3            3-5            3-6           2-4           2 -5          4-5      4-6     5-6

Normal time(week)                  3                8                6               5               4               13            2           2       6

Normal cost (Rs.)                     1800          60           1000           400         1500           300        120       700   350

Crash time (weeks)                    2               6                4                 2              4                10           1            1        4

Crash cost (Rs.)                         1900          100          1200         1000         1500          900        140       800   450

The indirect cost of the project is Rs.90/week

If it is necessary to complete the project in 17 weeks, at what cost it could be achieved ?

Section II

Q.3) a company which manufactures three products A,B and C requiring two resources  labor and materials and want to determine the optimal product mix that maximizes profit the following linear program was formulated to answer this:-

Maximize Z = 3 X1 + X2+5X3

Subject to                         6x1+3x2+5X3 <=45      (labor)

3X1+4X2+5X3 <=30       (material)

Where x1, x2, x3 are the units of products A, B, C product. Find the optimum product mix.                     (10)

Q.4) the Indian navy wishes to assign 4 ships to patrol 4 sectors of the sea. In some areas ships are to be on the lookout for illegal fishing boats, and in other sectors to watch for enemy submarines, so the commander rates each ship in terms of its probable efficiency in each sector. These relative efficiencies are given in the table below:-

Ship A B C D
1 20 60 50 55
2 60 30 80 75
3 80 100 90 80
4 65 80 75 70

 

On the basis of the rating shown , the commander wants to determine the patrols assignments producing the greatest over all efficiencies what is the optimal assignment ?                                           (10)

Q.5) given elow is a table taken from the solution process for a transportation problems.

Cost per unit (in Rs.)

Distribution centre

factory

1

2

3

4

availability

A

10

8

5000

7

12

5000

B

12

13

6

4500

10

1500

6000

C

8

7000

10

500

12

14

1500

9000

Demand

7000

5500

4500

3000

Answer the following question and answer briefly

a)      Is this solution feasible?

b)      Is this solution degenerate?

c)       Is the solution optimum? If not find the optimum solution.

d)      Does the problem have alternative optimum solutions?

Q.6) a farm owner is considering drilling a well. In the past only 85% of the wells had yielded water at a depth of 250 feet in the area. On the finding, no water at a depth of 250feets some persons drilled further down up to 300 feet but only 25% struck water at the depth. The cost of drilling Is Rs.35/foot. The farmer estimates that if he does not have his own well he will be have to pay Rs.15000 over the next 10yrs.(in PV terms) to buy water from a neighbor. The following decision could be optimal.

a)      Do not drill a well

b)      Drill up to 250 feet

c)       If no water is found at 250 feet drill upto 300 feet

d)      Draw a decision tree to represent the situation and determine the farm owner’s strategy under the EMV approach                                                                                                                                   (10)

 

 

 

activity Three time (estimated week)
1-2 1-1-7
1-3 1-4-7
1-4 2-2-8
2-5 1-1-1
3-5 2-5-14
4-6 2-5-8
5-6 3-6-15

 

 

 

 

 

 

 

 

Draw the project network

a)      Find the expected duration and variation for each activity.

b)      Find SD of project length

c)       What is the probability that the projected will be completed in 20 weeks or less?

d)      What should be the project due date so that probability of achieving it is 95%


Like it? Share with your friends!

0
Muthu Konar

a proud BMSite from V.k.krishna menon college, bhandup (E).

0 Comments


Warning: Undefined array key "html5" in /home/bmsnewco/public_html/wp-content/plugins/facebook-comments-plugin/class-frontend.php on line 140

Facebook comments:

This Website Is For Sale. Email us an offer we cannot refuse on [email protected] :)

X
Choose A Format
Personality quiz
Series of questions that intends to reveal something about the personality
Trivia quiz
Series of questions with right and wrong answers that intends to check knowledge
Poll
Voting to make decisions or determine opinions
Story
Formatted Text with Embeds and Visuals
List
The Classic Internet Listicles
Countdown
The Classic Internet Countdowns
Open List
Submit your own item and vote up for the best submission
Ranked List
Upvote or downvote to decide the best list item
Meme
Upload your own images to make custom memes
Video
Youtube and Vimeo Embeds
Audio
Soundcloud or Mixcloud Embeds
Image
Photo or GIF
Gif
GIF format